Monday, 5 October 2009

Shuffl sprint 5 plan

The plan for Sprint 5 has been posted at http://code.google.com/p/shuffl/wiki/SprintPlan_5.

Responding to research user desiderata, project activities are now diverging quite significantly from the original outline plan (other than user engagement still being a key activity at this stage).

The primary focus for this sprint will be to complete the initial data graphing display for the visualization use case, to demonstrate this to the researcher who requested this, and use that session to gather more detailed requirements for this aspect of Shuffl.

Secondary foci will be: improving aspects of the user interface, especially for workspace loading/saving, and creating some user documentation.

I also have an ongoing discussion with Ross Gardler about long-term sustainability and CLAs (contributor licence agreements) - see http://code.google.com/p/shuffl/issues/detail?id=9 for details.